Snaps

Pictures are added in chronological order. Scroll down for the latest.
(Most recent additions: 16 September 2016)

As you haven’t seen the church before: dust protection of interior features.
plastic_sheets1 20.10.15

28 October. Scaffolding beginning to be erected.
scaffold3 scaffold2scaffold1

scaffold4

Higher and higher…
scaffold6

The temporary roof protection in place, 17 November 2015
temp_roofcover2 temp_roofcover

…and inside didn’t escape.
_DSC7960

On 4 January 2016 the real work started! We were fortunate that we had all of Christmas under cover, but that cover has now been breached with the removal of the tiles.
The snaps of the outside work were kindly taken by Rob of Bakers.
20160104_121140 20160104_121219

Bags and bags of tiles came off!
20160113_120617
20160113_120631
By now, it’s getting a bit draughty inside!
daylight

15 January, and things are looking quite different. The old roof battens have been taken off and new ones are being installed over the new mesh that will take the plaster. The next five pictures are courtesy of Aiden Fothergill of Bakers, who included one of an exciting detail!
20160115_121804_resized 20160115_121659_resized

A picture of a piece of tile which was removed from the wall top, which Bakers' people all suspect is Roman. They commented: It has traces of pink mortar on it which is widely seen on reused Roman building materials in this area.

A picture of a piece of tile which was removed from the wall top, which Bakers’ people all suspect is Roman. They commented: It has traces of pink mortar on it which is widely seen on reused Roman building materials in this area.

There’s more information about this piece of tile on the Audio page.

20160115_121547_resized 20160115_124509_resized

Pile of old battens

Pile of old battens

More scaffolding had to be added on the inside, squeezing the rector out of his stall!

More scaffolding had to be added on the inside, squeezing the rector out of his stall!

End January and a welcome sign of progress: the prepared stone blocks have arrived

End January and a welcome sign of progress: the prepared stone blocks have arrived

"So where's that one to go...?"

“So where’s that one going…?”

And after the roof and stone work repairs were finished, we began the upgrading of the church’s heating system.

boiler room

boiler room

new boiler

new boiler

look at the size of that wrench!

look at the size of that wrench!

joints20160909_15355920160915_radiator20160915_pipe-bender